Please be aware that TfGM have advised that the installation of the fibre to link the A6MARR traffic light controlled junctions is now planned for completion by the end of January 2019, not mid-December as previously stated.
We have been informed that the delay is a consequence of the lead in time for additional specialist equipment that has been identified as being required and issues with ducting encountered on site.
With regards to the changes to the signal timings at the Macclesfield Road junction, TfGM have passed the information required to their contractor, Siemens, to carry out the works. This work will be carried out at the earliest opportunity in January once the required Siemens resource becomes available following the Christmas break.
The A6MARR Project Team will continue to work with TfGM to ensure that the works are completed at the earliest opportunity.